Figure 2. Text fixture.
NOTE
7. Preliminary Procedures. a. Trip 115 VOLT AC
The following paragraphs are divided into
CIRCUIT BREAKER (fig. 1) and 28 VOLT DC CIR
subparagraph a, performance check, and sub-
CUIT BREAKER of unit under test.
paragraph b, adjustments. When the per-
formance check is not within tolerance and no
c. Connect voltmeter to test jacks J1 and J4 of
adjustment is specified, the deficiency must be
power monitor test fixture with test leads.
d. Adjust voltmeter for 115 volt AC operation.
corrected before continuing with the procedure.