j. Carefully open NITROGEN TANK VALVE
(fig. 2) and
adjust WATER PUMP
NITROGEN REGULATOR (fig. 2) for 75 psia displayed on the digital display panel of the
PNEUMATIC PRESSURE STANDARD.
k. Close the INLINE VALVE
(fig. 2) and
monitor the
system for approximately 5
minutes to assure that there is no loss of pressure in the system.
NOTE
A solution of soap and water can be applied to each fitting to
1. If
there is no
loss of
pressure, turn
off NITROGEN TANK VALVE
(fig. 2) and
release the pressure via the VENT VALVE (fig. 2).
m. Remove the cap from the "T" fitting.
8. High Pressure
a. Performance Check
(2) Connect TI to the system, only connect the HIGH PRESSURE SIDE (fig. 3) of
the TI and leave the LOW PRESSURE SIDE (fig. 3) open to the atmosphere.
(4) Adjust WATER PUMP NITROGEN REGULATOR (fig. 3) fully ccw.
(5) Open NITROGEN TANK VALVE (fig. 3) and adjust WATER PUMP
NITROGEN REGULATOR (fig. 3) to pressurize the system to 75 PERCENT OF FULL
SCALE, then carefully adjust WATER PUMP NITROGEN REGULATOR (fig. 3) for FULL
SCALE indication on the TI.
of the TI and monitor the TI for leaks.
(7) If the TI appears to lose pressure, check all fittings for leaks. If no leaks are
detected, the TI has a leak and should be replaced.
(8) If TI maintains a FULL-SCALE indication, fill in the calibration data sheet.
b. Adjustments. No adjustments can be made.
7