TB 9-4935-552-50-2
e. The ITS and IR
probe will be
calibrated in
sections IV and VI
respectively.
NOTE
The following paragraphs are divided into performance checks
and adjustments. Make adjustments only when performance
checks are out of tolerance. If no adjustment is specified and
the performance check is out of tolerance, correct the deficiency
before continuing.
7. Equipment Setup
a. Request assistance of an experienced LCSS technician to operate and program the
LCSS test station.
NOTE
The alignment test stand is part of the EOTS, 4931-01-071-
1646.
b. Assemble the alignment test stand in the ITS configuration and mount the
Figure 1. Intensity test source - equipment setup.
c. Connect the radiometer A2 to system power supply A5 using cable provided.
d. Deenergize circuit breakers on source/detector adapter power supply 2A1A1.
5